RESOURCES / Ohr

The right choice of materials

How a comparison of steel, concrete and hybrid structures helped realise the slender cantilevered roof at Izmir’s House.

Case Studies

CS 002 · Study 2021–2023 · Rev 02 October 2026

Izmir’s House in Putrajaya, showing the completed slender cantilevered roof

Photography: C2 Builder

Rigorous engineering brings value even for small-scale projects — realising architectural ambition, improving buildability and delivering considerable cost savings.

At Izmir’s House in Putrajaya, an existing steel scheme designed by others used deep beams that could not achieve the intended slim profile of the long cantilevering roof. The appointment began with optimising that scheme. A comparison with reinforced-concrete and hybrid alternatives was then initiated alongside the steel optimisation, before subsequent novation to the design-and-build contractor.

6.5 m

Critical roof cantilever governing the study.

8.5 m

Critical column height governing the study.

75 mm

Tapered roof edge in the assessed schemes.

01 / The brief

Meeting the architectural intent

The architectural intent called for a roof that projected well beyond its supports while retaining a slender edge. Structural behaviour, roof depth and column proportions had to be considered together within a construction budget of RM2.1 million.

The architect’s conceptual vision for Izmir’s House, showing the slender cantilevered roof and glazed façade

The architect’s conceptual vision

The architectural visualisation shows the long cantilevering roof, slender edge and expansive glazed façade that informed the structural studies.

Architectural visualisation: ODE.

The structural alternatives were developed around the architect’s original vision, retaining the slender roof profile and open glazed spaces as the material strategy evolved.

02 / The initiative

Optimising the steel and assessing alternatives

The study was initiated with the architect and client to demonstrate how alternative material choices could achieve the intended slender roof profile while influencing buildability and construction cost. Reinforced-concrete and hybrid schemes were developed alongside the steel optimisation, enabling informed choices about the structural system. Steelwork optimisation also achieved considerable savings against the original steel design.

Material choice also had to reflect how the house would be built. For a small project in Malaysia, securing a suitable steelwork subcontractor with the required fabrication and workmanship quality can be challenging. The study considered constructability alongside cost and architectural expression.

03 / The evidence

Three schemes, one architectural ambition

Historical estimates for the structural options assessed. These are option costs, rather than total house construction costs.

01 / Optimised steel

Steel

Steel structural model from the comparative study

RM399,000

Historical structural option estimate

Roof member305 × 165 × 46 UB
Roof edgeTapered to 75 mm
Study positionOptimised steel alternative

02 / Subsequently adopted

Reinforced concrete

Reinforced concrete structural model from the comparative study

RM193,000

Historical structural option estimate

Roof slab200 mm reinforced concrete
Roof edgeTapered to 75 mm
Columns200 × 400 mm reinforced concrete

03 / Studied alternative

Hybrid

Hybrid structural model from the comparative study

RM201,500

Historical structural option estimate

Roof slab200 mm reinforced concrete
Roof edgeTapered to 75 mm
Columns150 × 200 mm RHS steel

RM206,000 lower: the reinforced-concrete estimate was approximately 52% below the assessed steel option. The hybrid estimate was RM8,500 above the concrete alternative.

The saving achieved through steel optimisation against the original design is separate from this comparison; the original steel-design cost is not quantified here.

04 / The decision

From comparative study to concrete construction

  1. Before novation: The material comparison was initiated with the architect and client and developed alongside the steel optimisation, establishing an informed basis for selecting the structural system.
  2. The study: the hybrid offered a balance between architectural appearance and structural function at a cost close to all-concrete. The comparison also demonstrated the suitability of concrete for the architecture and scale of the project.
  3. Design and build: The design-and-build contractor proceeded with the reinforced-concrete option. The appointment expanded from initial optimisation to responsibility for the structural design, continuing through construction and project completion following novation.

The completed house uses a reinforced-concrete roof and slender concrete columns to realise the intended proportions and long cantilever.

Reinforced-concrete roof and slender concrete columns during construction at Izmir’s House
Realising the slender architectural formThe reinforced-concrete roof and slender columns during construction show how the long cantilever and intended proportions were realised.

Explore Izmir’s House →

Study basis · 2021–2023

C35 concrete RM420/m³; reinforcement RM5,000/t; structural steel RM8,500/t; profiled metal deck RM300/m². Rates were current at the time of assessment. The comparison informs material selection and does not represent a final construction account.

CS 002 · Source Rev 01 · Web edition October 2026, updated to reflect the completed reinforced-concrete scheme.