RESOURCES / Ohr

Shaping the brief through informed choices

How material placement and coil-stacking arrangements affected factory floor loading, foundation design and estimated construction costs.

Case Studies

Metal sheet factory — owner-selected hero

Ohr initiated this study with the client to demonstrate how the placement and stacking of materials on the factory floor could significantly affect engineering requirements and construction costs. By examining the proposed operations together, we helped the client make informed choices about the investment in their new facility.

01 / Establish the operational needs

Establishing the floor loads

Work with the client to understand where materials would be stored, how they would be stacked and the weights the floor would need to support.

Ohr established the floor loads from the coil-stacking arrangements provided by the client, translating the proposed storage requirements into a basis for structural design.

FIGURE 01 / CLIENT'S STACKING ARRANGEMENTS

Block D & E · Raw-material storage

Original Block D and E stacking diagram, showing 15-tonne lower coils and 10-tonne upper coils
Lower tier · Coil C15 tonnes
x = 1,524 mm
y = 1,219 mm
Upper tier · Coil A or B10 tonnes
x = 1,219 mm
y = 1,219 mm
134kN/m² imposed load

Block F · Raw-material storage

Original Block F stacking diagram, showing 25-tonne lower coils and 15-tonne upper coils
Lower tier · Coil C25 tonnes
x = 1,980 mm
y = 1,219 mm
Upper tier · Coil A or B15 tonnes
x = 1,524 mm
y = 1,219 mm
165kN/m² imposed load
Client-provided coil-stacking arrangements from the original loading study. The original diagrams are retained; their weights, x and y values and imposed loads are set out as readable text.

02 / Show the engineering implications

Assessing how the floor space would be used

Translate the proposed arrangements into floor loads, then assess how different choices affect slab depths, pile sizes, pile spacing and estimated construction costs.

Ohr assessed how the proposed use of the floor space—for raw-material storage, production and finished goods—affected the design requirements and subsequent construction costs.

FIGURE 02 / FLOOR USE AND BAY DEFINITIONS

Scroll across the plan to inspect the detail →

Source floor-zoning plan: Zone A raw material at left, Zone B production at centre, Zone C finished product at right; source EB and IB markers retained
Zone ARaw-material storage4,756 m² on zoning plan
Zone BProduction coils5,424 m² on zoning plan
Zone CFinished product2,718 m² on zoning plan

Perimeter bays (EB): the first two bays from the building perimeter. Internal bays (IB): the rest of the floor. EP and IP denote the piles supporting perimeter and internal bays respectively.

The source plan is retained in greyscale, with its geometry and markers unchanged. Areas shown on the zoning plan differ from the areas used in the source cost schedules; they are kept distinct below.

Material placement shapes the design

These three examples show how alternative coil-stacking requirements changed the slab and foundation solution and its estimated cost.

FIGURE 03 / COMPARATIVE DESIGN-STAGE STUDY

Scroll across to compare all three options →

Zone A — three illustrative coil-stacking options from the original study
Zone A
Raw-material storage
Two-tier stackingSource option 1Heavier two-tier stackingSource option 3Heavier three-tier stackingSource option 5
Stacking arrangement15-tonne coils below
10-tonne coils above
25-tonne coils below
15-tonne coils above
25-tonne coils below
Two tiers of 15-tonne coils above
Imposed load · kN/m²134165226
Pile grid · m2.25 × 2.252 × 22 × 2
Slab thickness · mm
Internal / perimeter bays
225 / 275200 / 250250 / 325
Square precast piles · mm
Internal / perimeter
350 / 400350 / 400450 / 450
Floor slab · RM/m²477481572
Piling · RM/m²1,8312,2414,112
Slab + piling · RM/m²2,3082,7234,684

Dimensions are shown as internal / perimeter. All piling is square precast concrete. Costs are indicative study estimates, not current quotations.

Selected Zone A raw-material options 1, 3 and 5, transcribed from the original comparison schedule. The source uses a floor area of 4,725 m² for this cost assessment. Source component values and totals are retained as reported; rounding means they may not sum exactly.

The study made the connection between storage arrangements, floor loading and construction provision tangible.

These options provide different storage capacities; the cost differences are not like-for-like savings or savings realised in construction.

03 / Support an informed investment

Supporting an informed decision

Give the client a clear comparison of operational capacity and construction cost, so the design brief reflects considered choices about the new facility.

Ohr presented the study table to the client, bringing together the loading options, slab and pile requirements, and estimated costs to support an informed decision on the design requirements.

Full supporting schedule · Zone A and Zone B

The complete schedule from the third source visual is reproduced below. Shaded Zone A rows are the three examples compared above. The other source options are retained for context.

Zone A · Stacking of raw material

Source cost-schedule floor area: 4,725 m²

Scroll across for component costs and totals →

OptionCoil tiers¹
tonnes
Load
kN/m²
Pile grid
m
Slab²
mm
Piles²
mm square
Slab
RM/m²
Slab
RM million
Piling
RM/m²
Piling
RM million
Total
RM/m²
Total
RM million
115 / 101342.25 × 2.25225 / 275350 / 4004772.2531,8318.6512,30810.903
215 / 10 / 101872 × 2225 / 275400 / 4004912.3182,73112.9063,22215.224
325 / 151652 × 2200 / 250350 / 4004812.2742,24110.5902,72312.865
425 / 252062 × 2250 / 300400 / 4505082.4012,95013.9413,45916.342
525 / 15 / 152262 × 2250 / 325450 / 4505722.7024,11219.4304,68422.132

Zone B · Stacking of production material

Source cost-schedule floor area: 4,725 m²

OptionCoil tiers¹
tonnes
Load
kN/m²
Pile grid
m
Slab²
mm
Piles²
mm square
Slab
RM/m²
Slab
RM million
Piling
RM/m²
Piling
RM million
Total
RM/m²
Total
RM million
125812.5 × 2.5200 / 225350 / 3504181.9741,3346.3051,7528.280
2151042.5 × 2.5225 / 275350 / 4004882.3061,3816.5261,8698.832

¹ Coil tiers are listed from bottom to top. ² Slab thickness and pile sizes are shown as internal / perimeter. Values are reproduced as reported in the source. Source schedule references to Note 7 are retained in the source image; no additional Note 7 is supplied on that visual.

Informed decisions from the outset

The exercise helped the client balance operational requirements with the cost of providing them. It established a considered basis for the design loads from the outset, avoiding reliance on a generic allowance that could provide unnecessary capacity in some areas or insufficient capacity in others.

STUDY BASIS / ORIGINAL ASSUMPTIONS

Reading the comparison

Material and cost basis

Concrete grade35
ConcreteRM370/m³
SteelRM5,200/t
350 mm square pileRM8,136/pile
400 mm square pileRM10,341/pile
450 mm square pileRM15,569/pile

Precast concrete piles

Grade C50 · jacked-in installation.

Size · lengthWorking load
350 mm square · 48 m890 kN
400 mm square · 48 m1,075 kN
450 mm square · 54 m1,475 kN

Area bases: the zoning plan labels Zone A as 4,756 m², Zone B as 5,424 m² and Zone C as 2,718 m². The Zone A and Zone B cost schedules each state 4,725 m². The source does not reconcile these figures; the unit-cost comparisons above follow the original Zone A cost schedule.

Illustrative options from the original design-stage study. Estimates use the study’s assumed rates and exclude pile caps and formwork. Pile sizes vary between internal and perimeter bays where shown. These options provide different storage capacities; the cost differences are not like-for-like savings or savings realised in construction.

Source: 23003_Loading study_rev 00_mkp.pptx · September 2023 · stacking, zoning and Zone A/B comparison sheets.