Kapar Power Plant

Kapar, Selangor

Kapar Power Plant

Establishing the capacity of an existing structure to accommodate heavier equipment.

Four cooling-water pumps at Kapar Power Plant were scheduled for replacement with heavier units, requiring an assessment of the existing supporting structure to establish whether strengthening was necessary.

Understanding the existing structural capacity

A desktop structural assessment was undertaken using finite element back-analysis to evaluate the behaviour of the supporting structure under the increased equipment loads. The back-analysis provided a more rigorous understanding of the load distribution and available structural capacity.

Engineering assessment over unnecessary intervention

The assessment demonstrated that the existing structure had sufficient capacity to accommodate the heavier replacement pumps without strengthening, avoiding unnecessary structural intervention and its associated cost and disruption to the power plant.

Client

Architect

Design and Build Contractor

Project Manager

Interior Designer

Years

2015

Size

Project Cost

Services

Structural Forensics

Structural appraisal

Remedial design

Project Status

Completed